Substation Equipment

Testing, commissioning and protection coordination

Pre-commissioning and periodic tests are performed to IEC and IEEE requirements for reliable, stable and safe network operation. The service covers breakers and instrument transformers through digital relay commissioning and equipment protection.

Substation Equipment
Substation EquipmentBorna Energy Pishro

Specialized services list

Sub-services

Medium- and high-voltage breaker testing

Contact resistance, opening and closing timing, simultaneity, insulation, leakage current and Trip/Close coil tests.

CT, VT and CCVT testing

Ratio and polarity, CT saturation curve, secondary burden, winding resistance and CCVT insulation tests.

Disconnectors and interlock testing

Contact resistance, interlock operation, mechanical mechanism checks and functional verification.

Protection relay testing and coordination

Functional relay, input, output and Trip tests, parameter setting, operating curves and protection coordination.

Digital protection troubleshooting and commissioning

Unwanted Trip and Event Record analysis, control-circuit checks, numerical-relay parameterization and Logic/Function tests.

Equipment protection-system testing

Testing and commissioning for transformer, generator, feeder, motor, busbar and transmission/distribution-line protection.